Tracking pixel
Roebuck Plaza

Roebuck Plaza

We’ve summarised all the key safety information for you to make it as easy as possible for you to access and understand, but if you’d like to know about any of this in more detail, please just get in touch. You can email us to request more information.

About your building

Address: Academy Street, Warrington, WA1 2PN.
Number of storeys: 9
Height: 29 meters
Number of apartments: 144
Year of construction: 2022
Responsible person: Emmanuel Oboh
Accountable person: Steve Coffey (Torus 62 Ltd)
Evacuation strategy: Stay Put (Defend in Place).

We carry out regular structural assessments of our buildings to assess their strength and stability. They involve experts inspecting the building’s framework, materials, and support systems to ensure everything is in good condition, helping to ensure the safety and longevity of the structure.

  • Who checks: Curtins
  • How often: Every 5 years. Last surveyed on 27 August 2024.

The construction of the building is concrete, brick external facade fire rated internal partitions and a series of flat roofs with some that can be utilized as roof terraces. On the ground floor is a concierge with office, plant and refuse storage, as well as commercial unites that are to be leased. Foundations – driven plies foundations. Ground floor – the suspended 250mm thick ground floor concrete slap spans between the ground beams is to comprise finishes.

A Fire Risk Assessment (FRA) is a report on the fire hazards within the communal areas of a building, as well the external walls and materials used. It’s carried out by an independent fire safety expert annually and explains the key safety measures in place and identifies any potential fire safety risks.

It also gives recommendations for us to follow if more safety measures are needed to prevent, control, and reduce the effects of a fire. Our FRAs are made available to the Fire and Rescue Service whenever necessary.

  • Fire Risk Assessment was completed by FCMS (Adam O'Dowd BSc DipFD TIFSM)
  • Date of latest Fire Risk Assessment: 11 June 2025
  • Next Fire Risk Assessment due: June 2026

Building maintenance and inspections

Equipment
Contractor
Maintenance Frequency
Automatic Doors and Gates Openview 6 monthly
Access Intercom Openview
Annually
Fire Doors - Communal FCS Live 3 monthly
Fire Doors - Flats Front Doors FCS Live Annually
Heating (Air source heat pumps, gas boilers, gas driers Sure Maintenance Annually
CCTV Openview Annually
Passenger Lifts Knowsley Lift Services Monthly
Passenger Lifts LOLER's OTIS 6 monthly
Communal Fire Detection System Fieldway LTD 6 monthly
Evacuation Alert System Fieldway LTD
6 monthly
Sprinkler Suppression System Fieldway LTD
Annually
Domestic Smoke / Heat Detection HMS At void or every 5 months
Dry Riser Fieldway LTD
6 monthly
Bin Chute Fire Suppression System Fieldway LTD
6 monthly
Emergency Lighting HMS Monthly
Lightning Protection Fieldway LTD Annually
Mains Water Services HMS 6 monthly
Fire Extinguishers Fieldway LTD
Annually
Electrical Testing (Communal EICR) HMS 5 yearly
Electrical Testing (Domestic EICR) HMS 5 yearly
Portable Appliance Testing (PAT) HMS Annually
Asbestos Torus Annually


Last service and maintenance information is available on request. If you'd like to know when the equipment in your block was last inspected or serviced, please contact us on 0800 678 1894 or email us at buildingsafety@torus.co.uk.